|
General Contractor’s Promise of
Payment Makes it Directly Liable to Sub-Subcontractor
On September 28, 2005, the Ontario Superior Court
of Justice released its decision in 1379691 Ontario
Ltd. v. Appugliesi.
The plaintiff was a sub-subcontractor who did
masonry work on a school project. When the plaintiff
was not paid by the subcontractor on time, it
complained to the general contractor and threatened
to walk off the job if it was not paid. At a meeting,
the subcontractor said it didn’t have the
funds to make the payment. The general contractor
wanted the plaintiff to complete their work and
asked them not to walk off the job. The general
told them that it would pay them “whatever
is owing, both past and future” and would
pay it out of the subcontractor’s holdback
account. The holdback account at that time contained
$75,000, more than enough to pay the plaintiff.
The general contractor told the plaintiff that
the payment would be made by the end of the month.
It promised that no other bricklayers would be
paid before the plaintiff received their payment.
The plaintiff accepted the offer and agreed to
continue working.
When the plaintiff remained unpaid, it brought
an action against the general and the sub for
payment. The general contractor argued that the
amount owing should be paid by the subcontractor.
The general contractor argued that its promise
to pay the plaintiff directly was at most an oral
guarantee, and as such was unenforceable under
section 4 of the Statute of Frauds. It also argued
that the promise made by its president at the
meeting that if the plaintiff agreed to stay on
the job, the general contractor would pay them
what they were owed by the end of the month, was
at most a gratuitous promise, made without any
consideration and missing essential terms. Again,
the Court disagreed. By the general contractor’s
own admission this was intended to be a binding
promise. The benefit to the general contractor
of having the plaintiff stay on the job so that
they could complete their work was recognized
and acknowledged by the general contractor. There
was ample consideration. The general contractor
did not promise to pay the plaintiff only if the
subcontractor failed to do so – it was clear
at the meeting that the subcontractor was unable
to make the payment. The plaintiff was looking
to the general contractor for immediate payment
and the latter agreed to pay them directly. This
was not a third party guarantee, but a direct,
first party promise. Based on this promise, the
general contractor was liable to pay the sub-subcontractor
directly.
|