|
General Contractor Cannot Drop Pre-Qualified
Subcontractor for Unreasonable Objections
Schaible Electric Ltd. v. Melloul-Blamey Construction
Inc.
On July 29, 2005, the Ontario Court of Appeal
upheld a lower court decision awarding damages
to a subcontractor after it was dropped by a general
contractor that had carried the subcontractor’s
bid.
General contractors submitting tenders for a
school project were required to carry electrical
and mechanical bids from companies that had been
pre-qualified by the school board. The plaintiff,
one of the pre-qualified electrical subcontractors,
submitted the lowest bid for the electrical work
for the project. The defendant carried the plaintiff's
bid in its tender, but later developed serious
concerns about the defendant’s ability to
complete the electrical work competently and expeditiously.
The defendant had been told by the project’s
architect and the owner’s site representative
that they were concerned about the plaintiff’s
ability to do the work in a timely manner. The
defendant contacted various electrical suppliers
and all came back with negative responses concerning
the plaintiff. Consequently, the defendant demanded
100% performance and labour and materials bonds,
which the plaintiff was unable to obtain. The
defendant then awarded the contract to the second
lowest bidder.
The court held that the defendant did not have
a reasonable objection to contracting with the
plaintiff. Although the defendant had obtained
some negative information about the plaintiff,
the plaintiff had been pre-qualified and had successfully
completed other projects for the owner.
The court also held that the defendant was not
entitled to demand performance and labour and
material bonds from the plaintiff in the full
amount of the subcontract price in the circumstances.
|