|
New Ontario Court of Appeal Decision
on “Contract A”
Transit Commission v. Gottardo Construction
Ltd.
On September 7, 2005, the Ontario Court of Appeal
released its decision in Toronto Transit Commission
v. Gottardo Construction Ltd.
When the TTC opened tenders it had received for
a major project, Gottardo was the lowest bidder.
Shortly after the tenders were made public, Gottardo
advised the TTC that it had made a $557,000 error
in the tender amount. Gottardo maintained that,
because of the error it was not obligated to honour
the tender price of $4,811,000. The TTC took the
position that Gottardo was bound. When Gottardo
refused to sign the contract, the TTC awarded
the contract to the next lowest bidder and sued
Gottardo claiming, among other alternative relief,
damages of $434,000, being the difference between
Gottardo’s tender price and the price at
which the work was ultimately carried out. CGU
Insurance Company of Canada (CGU) was also sued
by TTC, as it was the company that had issued
Gottardo’s bid bond.
The trial judge found that the TTC’s tender
instructions were such that a first contract,
referred to in the case law as “Contract
A”, had not come into existence upon the
opening of the sealed tenders, arguing that additional
documents had to be provided by Gottardo before
Contract A came into existence. These additional
documents were required by the tender instructions.
Once the documents were provided to the TTC, it
was apparent that an error had been made in the
tender amount. The trial judge found that Gottardo’s
mistake was discernable on the face of the documents
before the formation of Contract A, and therefore
that the TTC could not compel Gottardo to honour
the price and could not recover against CGU on
the bid bond. Consequently, she dismissed TTC’s
claim against Gottardo and CGU.
The Court of Appeal allowed the appeal, holding
that Contract A had been formed and that Gottardo
had breached this contract. The Court awarded
damages in the amount of $434,000 against both
defendants together with pre and post judgment
interest.
The Court clarified that acceptance or rejection
of the bid is not what leads to the creation of
Contract A. Acceptance or rejection is the end
point of the tender process. Once the tender is
accepted, the parties enter into the construction
contract referred to as Contract B. The fact that
certain steps are taken and certain documents
are to be produced by the tenderer after the submission
and opening of tenders will not delay the formation
of Contract A when the clear intent of the parties
is to be bound as of the opening of the tenders.
In this case, it was clear from the tender documents
that the parties intended to initiate contractual
relations the moment that the tenders were opened.
|