|
PREDICTING LIENABILITY:
The Ontario Court of Appeal decision in Kennedy
Electric
Charles G.T. Wiebe
It is safe to say that the mechanical and electrical
trade associations have been waiting with bated
breath for the Court of Appeal decision in Kennedy
Electric Limited v. Dana Canada Corporation, hoping
for a restatement of the legal principles that
determine whether their work constitutes a “supply
of services to an improvement.” under the
Construction Lien Act. The decision was released
on September 27, 2007 and, while it contained
some analysis of the principles (perhaps in obiter),
the decision stressed more the factual basis of
the exercise. Therefore, the decision may have
disappointed some.
The facts of the case are familiar. Dana had
a contract with Ford to build frames for a line
of pickup trucks. Dana owned a property in St.
Mary’s, Ontario and arranged under one contract
to build a building addition there for the assembly
line that would be used to build the truck frames.
Dana entered into a separate contract with Rumble
Automation to have Rumble design, build and install
the assembly line. Rumble designed, built and
tested the assembly line at its sites in Oakville
and Mississauga, and then disassembled and transported
the line in pieces to Dana’s building in
St. Mary’s. Part of Rumble’s work
was subcontracted to Kennedy Electric. Kennedy’s
responsibility was to disassemble the line, transport
it to St. Mary’s and install it in Dana’s
building.
The assembly line was massive and complex. There
were 100 mezzanine platforms and 165 robots. The
line was attached to the floor with some 2,000
to 3,000 mechanical and chemical bolts ranging
from one-quarter inch to three-eights of an inch
wide and from six to eight inches in length. The
line covered about 100,000 square feet and weighed
about 500,000 tons. It took Kennedy 2 ½
months with 165 trucks to disassemble, transport
and reassemble the line. Kennedy was not paid
and registered a lien against Dana’s property.
By the time of the Court of Appeal hearing Rumble
was bankrupt.
The trial judge made several findings of fact.
He found that Kennedy was not involved in the
connection of the line to any building services.
He found that the line could be readily disconnected
from the building without damaging the building.
Finally, he found that Dana had previously moved
some of its assembly lines from one plant to another.
The Court concluded that the line was “portable”
and that its installation was neither an integrated
construction project within the building nor was
it a free-standing improvement on its own.
Kennedy appealed to the Divisional Court where
the majority agreed with the trial judge, dismissing
the appeal. The majority adopted a “functionality
test” whereas Justice Chapnik in dissent
adopted a “reasonable person” test.
O’Driscoll J., speaking for the majority,
referenced a line of Ontario cases that indicated
that the issue turned on whether the work in question
was associated with the functioning of the building
itself as opposed to the functioning of the business
within the building.
Chapnik J. dissented. She criticized the reasons
below for giving undue weight to the “alleged
portability” of the assembly line. In her
view the issue was more one of whether a reasonable
person would consider whether the premises had
been improved by the installation of the assembly
line. In that context, according to Justice Chapnik,
other factors had to be considered: the intentions
of the parties, the purpose of the building (ie.
whether it was designed to house the assembly
line), the intended permanence of the assembly
line, the cost of the assembly line as opposed
to the building, and the proximity in time between
the building construction project and the assembly
construction project. When these factors were
considered, according to Justice Chapnik, the
assembly line installation could be viewed by
a reasonable person as being integrated with the
building project and therefore an “improvement.”
Kennedy appealed to the Court of Appeal urging
the Court to adopt the broader analysis of Justice
Chapnik which focused on the intentions of the
parties. In particular, Kennedy argued that the
Court should adopt the following factors: whether
the installation was an “integral part”
of the building’s systems or components
regardless of its portability; whether the installation
was done with “some idea of permanency;”
whether the installation was intended to remain
in place so long as it could be used for its intended
purpose or was economically viable; whether the
installation was connected to the properties’
utilities; whether the installation could be removed
as a unit or in parts; whether disassembling the
installation was difficult; and whether the building
was especially designed for the item in question.
The Court of Appeal found it unnecessary to express
any clear rule or principle in the circumstances
of the case. The Court of Appeal gave deference
to the trial judge’s finding of “portability”
as a finding of fact. As there was evidence to
support that finding of fact, the Court said that
an appellate court should not interfere with it.
The Court then concluded that it was open for
the trial judge to conclude that the installation
of the assembly line was not lienable in light
of his finding of portability. The Court went
on to state that the issue of what constituted
an “improvement” was primarily a finding
of fact for determination of the trial judge and
that different judges could reach different conclusions
on this issue as a result.
In what appears to be obiter, the Court did make
the following statement:
In most cases, the installation or repair of
machinery used in a business operated in a building,
particularly where the machinery is portable,
will not give rise to lien rights under the CLA.
On the other hand, where machinery is installed
in a building for the use of a business and is
completely and permanently integrated into the
building, a lien claim will arise. (emphasis added)
While perhaps not strictly an authoritative pronouncement,
this statement appears to signal the thinking
of the Court concerning equipment installation
cases and is therefore worth exploring. Arguably
the Court has in this statement signaled that
the legal principle that should guide a court
in its fact-finding exercise is the following:
the machinery has to be “completely and
permanently integrated into the building”
to be an improvement.
There appear to be two concepts in this statement.
The first is the concept of “integration.”
The Court did not define this term, but it was
explored by another court in a decision that was
quoted at some length by both the Divisional Court
and the Court of Appeal, namely the decision of
County Court Judge Boyle in the1995 British Columbia
case of Spears Sales & Services Ltd. v. Westpine
Fisheries Ltd. Here the issue was whether the
installation of a pumping system into a fish packing
plant gave rise to lien rights. The part of his
decision that was quoted by the Ontario Divisional
Court and Court of Appeal is the following:
Did the pumps become part of the realty? They
may have so been intended as between lessor and
this lessee but that is not determinative.
Based in considerable part upon the affidavit
filed on behalf of Westpine, my original focus
was upon the use of the building and the function
of the business in the building. That function
has been primarily fish packing. The pumping system
is an integral part of that function.
But the question must be answered by looking
not to the parties. The question is: are the pumps
an integral part of the function of the building?
The question does not concern the function of
the business it houses (although buildings and
improvements may function in specific ways to
suit a business). The question because of its
statutory basis must be answered in strict terms.
In this light this pumping system is not an improvement.
Judgment accordingly (emphasis added)
This quotation suggests a strict, objective functional
test for whether a machine was “integrated”
into the building. Judge Boyle expressly stated
that, being a statutory remedy, the interpretation
had to be “in strict terms.” He went
on to state that the test had to be an objective
one, namely not one necessarily determined by
the intentions of the parties. Finally, he stated
that the test concerning the lienability of the
machinery installation was a functional one, namely
whether the machinery became “an integral
part of the function of the building.”
We suggest that this is the thinking of the Court
of Appeal as well when it used the word “integrated.”
The Court quoted the strict interpretation requirement
from the 1960 case of Ace Lumber Ltd. v. Clarkson
Co. Ltd. The Court did not accept Kennedy’s
submission that the test outlined by Justice Chapnik
(which focused more on the intentions of the parties)
was essential to the definition of “improvement.”
Finally, the Court dismissed the submission from
Kennedy subcontractor, Cassidy, that the building
addition had no value or use other than to serve
the assembly line. The Court viewed the building
addition as having an independent set of functions
that had their own value. It is only a natural
conclusion from this that the question of lienability
turns on whether and the extent to which the machine
in question serves this independent building function.
The second concept in the Court’s above-noted
statement is this one: “completely and permanently
integrated” (emphasis added). The Court
here appears to be stating that a machine that
is otherwise serving the building function needs
to pass another test in order to be considered
to be a part of the improvement. This additional
hurdle appears to tie in to the concept of “portability”
that the Court expressly endorsed as a factor
in determining lienability. The Court stated at
one point that an installation that “is
moveable (ie. portable) and not an integral part
of the building” will not give rise to lien
rights.
What is significant about the decision on the
issue of “portability” is that the
Court appears to have focused on the findings
of fact of the trial judge concerning whether
the assembly line could be moved at all without
damaging the structure and whether other assembly
lines had been moved in the past in other situations.
The other facts that Kennedy focused on in its
argument (namely the cost and inconvenience of
moving the line and the intentions of the parties)
did not, in the Court’s view, create a reviewable
error by the trial judge. This suggests that the
Court views the issue of portability as a strictly
objective test of whether the machine can be and
has been moved and used elsewhere without damaging
the building.
What we are left with then concerning the Court’s
obiter statement is a concept of lienability that
may effect some movement in the law of lienability.
Arguably the concept of “integration”
is consistent with the line of Ontario cases stemming
from Hubert v. Shinder which requires that a lienable
machine must primarily serve a building function.
Such building functions would appear to be those
that pertain to every building – structure,
heating, air flow, lighting, plumbing, etc. What
may be a departure is the concept of the machine
being “completely and permanently”
integrated into the building. A machine that is
otherwise integrated into a building and its functions
may still not be lienable if it can be removed
and used elsewhere without damaging the building.
One wonders for instance whether the 1988 Ontario
case of Stacey Heating & Plumbing Supplies
Ltd. v. Tamasi would now be decided differently.
That case held that the installation of air conditioning
machines was lienable.
In short then, the Court of Appeal in the Kennedy
Electric decision has arguably provided some guidance
to the definition of “improvement”
under the Construction Lien Act, even though the
guidance may be oblique. The Court has clearly
held that the exercise of determining lienability
is a fact driven process in which portability
and integration are key factors. The Court also
appears to have affirmed a strict objective functional
test of lienability. In this regard, the decision
is arguably in line with the bulk of the case
authority. What may be an added dimension though,
namely the idea of “complete and permanent”
integration, will have to be worked out by the
courts in future cases.
Shortcut to: http://www.ontariocourts.on.ca/decisions/2007/september/2007ONCA0664.pdf
|