
This material is not intended to provide legal advice. Readers should not act upon information contained in this material without obtaining professional legal advice. This material may be considered advertising under the Rules of Professional Conduct of the Law Society of Upper Canada.
ENGINEERING FIRM LOSES ONE YEAR
LIMITATION PERIOD PROTECTION
29 C.L.R. (2d) 212
by
[of Glaholt & Associates]
Engineers may lose their one year limitation protection under the Professional
Engineers Act of Ontario where they are joined as third parties for contribution as
tortfeasors in disputes between owners and contractors. An action (Con-Drain Co. (1983)
Ltd. v. Jane-Langstaff Developments Ltd., (1995), 26
C.L.R. (2d) 139, 44 C.P.C. (3d) 249 (Ont. Gen. Div.)), was commenced by a contractor to
recover the cost of repair work to a major manhole that was part of a sewer system on land
owned by a developer. In its defence, the owner/developer counterclaimed and added the
adjacent owner/developer and sewer contractor as defendants to the counter claim.
These last defendants added the engineering firm responsible for the design and
construction supervision of the
sewer system that ran through both pieces of land as a third party to the action.
In their third party claim the defendants specifically alleged that the engineering firm
was negligent in failing to:
(a) Provide adequate specifications for the sewer work;
(b) adequately supervise the work of the contractors;
(c) identify and arrange for the correction of defective work;
(d) act on the contractors' report of deficiencies respecting the manhole.
On a motion to dismiss the third party claim against the engineering firm as being out of
time, the Court explored the legislation governing engineers and engineering firms namely,
the Professional Engineers Act, R.S.O. 1990, c. P.28. Section 47 of the Act provides a one
year limitation period after the engineering service has been provided within which the
engineers may be sued. Since the twelve month limitation period referred to in s. 47 of
the Act had expired from the date the engineering services were provided, the limitation
period under the Act had run out.
However, the Court also examined the Negligence Act, R.S.O. 1990, c. N.1, in order to
determine whether the time limitation period under s. 47 of the Professional Engineers Act
had been overridden.
Section 8 of the Negligence Act provides that no proceedings for contribution or indemnity
against another
tortfeasor are defeated by the operation of any statute limiting the time of the
commencement of the action against the other tortfeasor provided the proceedings are
commenced (against that tortfeasor) within one year of judgment or settlement.
[of Glaholt & Associates]