In Land Design Inc. v. Ontario Infrastructure and Lands Corp., 2026 ONSC 4690 (“Land Design”), the Ontario Divisional Court considered whether Infrastructure Ontario’s decision to disqualify a proponent from a public procurement process, following contact with the Premier of Ontario and a Minister of the Crown, was reasonable and procedurally fair.
The decision addresses when public procurement decisions are subject to judicial review, how prohibited contact provisions in requests for proposals are interpreted and enforced, and the scope of a procuring authority’s discretion to disqualify a proponent to protect fairness, and perceived fairness, of a competitive process.
Factual Background and Procedural History
The dispute in Land Design arose from a request for proposals (“RFP”) issued by Ontario Infrastructure and Lands Corporation, operating as Infrastructure Ontario (“IO”), for construction administration services in connection with the redevelopment of Ontario Place in Toronto (the “Project”). Land Design Incorporated (“LANDinc”), a landscape architecture and design firm, had previously performed design work on the Project, including developing a three-dimensional model of the proposed redevelopment (the “3D Model”).
The RFP prohibited proponents from lobbying to influence the procurement process and restricted contact with specified individuals, including the Premier of Ontario and Members of Provincial Parliament, on matters related to the RFP process. The RFP also afforded IO discretion to disqualify proponents for prohibited contact or attempted contact.
On May 11, 2026, shortly after LANDinc entered the RFP process, a junior LANDinc employee met the Premier of Ontario at an event and discussed the 3D Model. Following the Premier’s expression of interest in viewing the model, the employee contacted the Premier’s office to arrange a visit. On May 26, 2026, the Premier and Ontario’s Minister of Tourism attended LANDinc’s offices, viewed the 3D Model, and engaged in discussions with LANDinc personnel (the “Visit”).
After learning of the Visit, IO raised concerns that LANDinc had contravened the RFP’s prohibited contact provisions. Following an investigation and written submissions from LANDinc, IO disqualified LANDinc from the RFP process on June 11, 2026, and subsequently upheld its decision on reconsideration. LANDinc commenced an application for judicial review, challenging the reasonableness and procedural fairness of its disqualification.
The Decision
Jurisdiction to Judicially Review Public Procurement Decisions
At the outset of its analysis, the Court considered whether IO’s decision was subject to judicial review under the Judicial Review Procedure Act, RSO 1990, c J.1.
The Court noted that judicial review is “directed at public decision-making” and is available only where the impugned decision involves an “exercise of state authority” that is “sufficiently public in character”.
In determining whether that threshold was met, the Court considered the factors identified in Air Canada v Toronto Port Authority, 2011 FCA 437, including the nature of the decision-maker, the character of the decision, its relationship to statutory or governmental functions, and the suitability of public law remedies.
The Court noted that public procurement decisions are not automatically subject to judicial review merely because they involve a public authority. Rather, jurisdiction must be assessed on a case-by-case basis, having regard to the particular circumstances of the decision under review.
In this case, the Court identified several factors supporting the availability of judicial review. These factors included the significant public interest associated with the redevelopment of Ontario Place, the substantial nature of the proposed services contract, and the involvement of senior elected officials in circumstances raising concerns about the integrity of the procurement process. Of particular importance was the purpose of the prohibited contact provisions, which sought to prevent proponents from obtaining, or appearing to obtain, an unfair advantage through contact with political officials.
Project scale and contract value alone would not justify judicial review; it was their combination with concerns about the integrity and perceived independence of the procurement process that gave the decision a sufficiently public character. The Court therefore concluded that it had jurisdiction to review IO’s disqualification decision.
Reasonableness of IO’s Disqualification Decision
Having established jurisdiction, the Court considered whether IO reasonably concluded that LANDinc had contravened the RFP’s prohibited contact provisions and, if so, whether disqualification was a reasonable exercise of IO’s discretion.
In challenging the finding of prohibited contact, LANDinc advanced two principal arguments. First, it argued that the Visit was consistent with its legitimate expectations arising from an earlier meeting with IO personnel. Second, it submitted that IO had failed to undertake an adequate investigation into the circumstances surrounding the Visit.
With respect to legitimate expectations, LANDinc argued that an earlier meeting at its offices with IO personnel, which occurred after the RFP process had commenced, led it to reasonably believe that the subsequent Visit involving the Premier and the Minister was similarly permissible.
The Court rejected this argument, noting that the doctrine of legitimate expectations generally concerns representations about the procedures a decision-maker will follow, rather than the substantive outcome of a decision. The Court also observed that LANDinc had not properly advanced a legitimate expectations argument in its original submissions to IO or its request for reconsideration.
The Court further distinguished the earlier meeting with IO personnel from the Visit. In particular, the Visit did not arise as a matter of course under LANDinc’s existing contractual relationship with IO, but resulted from LANDinc leveraging its previous work on the Project to arrange a meeting with senior political officials. In those circumstances, the Court concluded that the earlier meeting did not provide a reasonable basis for LANDinc to believe that contact with the Premier and the Minister was permitted during the RFP process.
The Court also rejected LANDinc’s argument that IO had failed to conduct an adequate investigation. LANDinc maintained that IO ought to have obtained additional information from the Premier’s office and other government officials to determine the circumstances surrounding the Visit. However, the Court concluded that IO had sufficient information to determine whether the RFP had been contravened, including LANDinc’s own account of the events and the correspondence arranging the Visit.
While LANDinc disputed whether it had initiated contact with the Premier, the Court considered that distinction to be of limited significance. The evidence established that the initial encounter developed into a planned visit over approximately two weeks, during which LANDinc personnel coordinated with the Premier’s office. The Court emphasized that the responsibility for complying with the RFP rested with LANDinc, regardless of whether the Premier had initially expressed interest in viewing the 3D Model.
Having concluded that IO reasonably found a contravention of the RFP, the Court considered whether disqualification was a reasonable response.
LANDinc argued that the disqualification decision was arbitrary and procedurally unfair. The Court rejected this argument, emphasizing that the RFP expressly authorized IO to disqualify a proponent for prohibited contact.
The Court distinguished between an incidental encounter with a prohibited person and the circumstances surrounding the Visit. It acknowledged that a chance encounter, or an initial contact that went no further, would likely not, without more, warrant sanction. The appropriateness of disqualification must instead be assessed in light of the circumstances and the need to protect the integrity of the procurement process.
Here, however, the initial encounter had developed into a planned meeting involving the Premier, a Minister of the Crown, and senior LANDinc personnel. The Court found it reasonable for IO to conclude that LANDinc had leveraged its position as an incumbent service provider to secure access to senior political officials in a way that could appear to give it an unfair advantage over competing proponents.
The Court stressed that the integrity of a public procurement process depends not only on whether proponents obtain an unfair advantage, but also on whether the process is reasonably perceived as fair by all participants.
The Court therefore concluded that IO’s decision to disqualify LANDinc was a reasonable exercise of its discretion and was consistent with its obligation to preserve the fairness and appearance of fairness of the RFP process.
Procedural Fairness
LANDinc also argued that IO had breached its duty of fairness by disqualifying it from the procurement process. The Court rejected this argument, holding that IO’s duty to administer the RFP fairly was owed not only to LANDinc, but to all proponents.
The Court observed that even-handed enforcement of procurement rules is an important component of that duty. Where conduct raises concerns about a potential breach of the RFP, the procuring authority’s investigation and response may serve its obligation to ensure that no proponent gains, or appears to gain, an unfair advantage.
IO had notified LANDinc of its concerns, identified disqualification as a potential consequence, and gave LANDinc an opportunity to respond. Following the initial decision, IO also considered LANDinc’s further submissions on reconsideration. The Court was therefore satisfied that the process was procedurally fair.
The Court also rejected LANDinc’s attempt to characterize its disagreement with IO's substantive findings as a procedural fairness issue. The Court distinguished between the fairness of the process followed and the reasonableness of the substantive decision, concluding that LANDinc had not established a breach under either analysis.
Breach of Contract Arguments
Finally, LANDinc advanced alternative arguments founded on breach of contract.
The Court concluded that it lacked jurisdiction to determine those claims on an application for judicial review, as contractual claims fall within the jurisdiction of the Superior Court of Justice.
The Court nevertheless recognized that, in appropriate circumstances, interim relief may be available where a proceeding has been brought before the Divisional Court but ought to have been commenced before the Superior Court of Justice, and where requiring the parties to pursue that alternative process could occasion an injustice.
In declining to intervene in this case, the Court observed that LANDinc’s contractual claims appeared weak. In particular, the RFP expressly provided that the procurement process did not create contractual relations between IO and proponents.
The Court also rejected the suggestion that a binding non-disclosure agreement entered into in connection with the RFP rendered the procurement process itself contractual in nature.
Given these conclusions, the Court declined to grant interim relief and dismissed the application.
Commentary
The decision in Land Design provides guidance on the circumstances in which public procurement decisions may be subject to judicial review and the discretion afforded to procuring authorities when enforcing the rules governing competitive procurement processes.
The Court’s treatment of jurisdiction is particularly informative. Although it accepted jurisdiction, the Court did not recognize a general right of judicial review in procurement matters; proponents seeking review will need to show that the decision is sufficiently public in character.
In that regard, the decision suggests that concerns involving the integrity and perceived independence of a public procurement process may provide a stronger basis for judicial review than the scale or financial significance of the project alone.
The Court’s analysis of the prohibited contact provisions also has practical implications for proponents participating in public procurement processes.
Notably, the Court's conclusion did not depend on a finding that LANDinc had engaged in deliberate lobbying or had actually obtained an advantage over competing proponents. Rather, the concern was that the Visit could reasonably be perceived as conferring an unfair advantage, particularly given LANDinc’s existing involvement in the Project and its access to senior political officials.
The test is not only whether particular conduct is intended to influence a procurement process, but whether it could reasonably appear preferential.
At the same time, the Court recognized that not every instance of prohibited contact will necessarily warrant disqualification. The discretion to disqualify a proponent must be exercised reasonably and in light of the particular circumstances. The distinction drawn by the Court between a chance encounter and a subsequently arranged meeting illustrates the importance of assessing both the nature of the contact and the conduct that follows.
For proponents, including consultants and contractors involved in large public infrastructure projects, the decision also highlights the risks associated with participating in successive stages of a project. Existing involvement may create legitimate opportunities for interaction with project stakeholders, but it does not relieve a proponent of its obligations under a new procurement process.
The Court’s observations concerning LANDinc’s internal compliance processes are particularly relevant. Although the initial contact arose from an encounter involving a junior employee, the Visit was subsequently arranged over approximately two weeks, with senior LANDinc personnel involved in the communications. The Court observed that there had been sufficient opportunity for those responsible for compliance to recognize that the Visit could contravene the RFP.
Procurement requirements, particularly restrictions on communications with specified individuals, should be communicated and understood throughout an organization, not only by the bid team. Junior employees may not appreciate these restrictions so proponents should ensure that staff at all levels understand them and that potential issues are identified early.
Ultimately, Land Design confirms that procurement fairness is owed to all participants: where a proponent’s conduct creates a reasonable perception of unfair advantage, disqualification may be justified even without evidence that the outcome was actually influenced.