What happens when a subcontractor whose price was carried into a successful bid, decides it no longer wants to do the work? Often, the subcontractor will argue that no contract was ever formed, because no subcontract was signed and the parties never agreed on all of its terms. In Manorcore Group Inc. v. IBL Structural Steel Limited, 2026 ONSC 4517 (“Manorcore”), the Ontario Superior Court of Justice rejected that argument. In doing so, provided a helpful reminder of how of the “Contract A/Contract B” tendering framework operates as between contractors and subcontractors.
Background
Manorcore Group Inc. (“Manorcore”), a general contractor, submitted a tender in March 2018 for the construction of an addition to the Wal-Mart Canada Corp. (“Wal-Mart”) store at the Pen Centre in St. Catharines. IBL Structural Steel Limited (“IBL”), a structural steel supplier and installer with whom Manorcore had no prior business relationship, provided Manorcore with an unsolicited quotation dated March 7, 2018 (the “Quotation”) to supply and erect the structural steel for the project. After verbal discussions between the parties, the lump sum price in the Quotation was increased to approximately $670,000.
Manorcore carried IBL’s price in its bid and identified IBL as its structural steel provider. Wal-Mart awarded the contract to Manorcore on April 13, 2018.
At Manorcore’s request, IBL provided a revised quotation on May 14, 2018 (the “Revised Quotation”), which adjusted the price of steel to account for newly imposed tariffs and adopted an alternate layout, for a total price of $690,000 plus HST. Although the form of the Revised Quotation provided for the signature of both parties, Manorcore never signed it. Instead, on May 15, 2018, Manorcore sent IBL its standard form Letter of Intent (the “LOI”), which IBL never signed.
The parties met on May 23, 2018 to discuss scope and schedule. At the end of the meeting, and as subsequently confirmed in writing, IBL advised that it would not be proceeding with the job. Manorcore requested further meetings to resolve the issue, but IBL maintained its position. Manorcore then retained Steelcon Fabrication Inc. (“Steelcon”), the second-lowest bidder, to perform the work, and sued IBL for the $271,200 in additional costs that it incurred as a result.
The Positions of the Parties
IBL relied on ordinary principles of offer and acceptance, arguing that the Revised Quotation was never accepted, and that the LOI was a counteroffer which IBL never accepted. Manorcore, in turn, relied on the law of tender, arguing that a binding contract arose when Wal-Mart accepted its bid.
The Decision
Justice Reid sided with Manorcore. The Court applied the Contract A/Contract B regime established in R. v. Ron Engineering & Construction (Eastern) Ltd., [1981] 1 SCR 111, and the Court of Appeal for Ontario’s decision in Naylor Group Inc. v. Ellis-Don Construction Ltd., (1999) 43 OR (3d) 325 (CA). It confirmed that the framework applies equally between contractors and subcontractors and that, unlike in ordinary contract law, communication of acceptance is unnecessary in the tendering environment. The subcontractor must maintain its bid, and the successful contractor is obligated to enter into a subcontract on the terms of the subcontractor’s proposal, absent a reasonable objection. Logically, the Court held, those obligations also operate in reverse: the subcontractor is bound to enter into Contract B unless it has a reasonable objection.
Applying these principles, the Court found that Contract A was formed when Manorcore submitted its bid using IBL’s price and naming IBL as its steel provider, and that Contract B came into existence when Wal-Mart accepted Manorcore’s bid. Because Contract B was already in effect, it did not matter that the Revised Quotation was later prepared, delivered, and never signed.
The more difficult question was whether IBL had a reasonable objection sufficient to relieve it of its obligations. The Court found that neither a perceived threat of litigation, nor the lack of a signature on the Revised Quotation or the LOI, constituted a reasonable objection. IBL also pointed to a number of terms in the LOI that were not contained in the Revised Quotation, including templates for drilling and anchor-setting and a $5 million insurance requirement. The Court accepted that major differences could theoretically vitiate the contract, as what is "reasonable" depends on the facts of the case.
Ultimately, however, the Court found it unnecessary to decide whether those differences were significant. The Revised Quotation was stated to be based on the CISC Code of Standard Practice for Structural Steel, which provides that the governing contract is the CCA 1 standard form subcontract. The CCA 1 contains comprehensive dispute resolution provisions, including an obligation to make all reasonable efforts to resolve disputes by amicable negotiation. Rather than engage in that process, IBL simply walked away. As the Court held, where the parties are required to negotiate a resolution of any dispute and one party fails to do so, that party cannot be said to have made a reasonable objection.
On damages, the Court awarded Manorcore the full $271,200 claimed, being the difference between Steelcon’s price of $1,050,900 (including HST) and IBL’s price of $779,700 (including HST), together with prejudgment interest. The Court rejected IBL’s suggestion that Wal-Mart may have reimbursed Manorcore as speculative, given Manorcore’s stipulated price contract with Wal-Mart.
Takeaways and Practice Tips
First, Manorcore confirms that, in the tendering context, a subcontractor’s obligations can crystallize well before any subcontract is signed. A subcontractor whose price is carried in a successful bid will generally be bound to enter into a subcontract on the terms of its bid, and cannot rely on the absence of a signature, or on ordinary offer and acceptance principles, to escape that obligation.
Second, while a subcontractor may be excused where it has a reasonable objection, that objection will be assessed on the facts of each case. Notably, where the parties’ documents incorporate, even indirectly, a dispute resolution process such as that contained in the CCA 1, a party that refuses to engage in that process before walking away will have difficulty establishing that its objection was reasonable.
With that in mind, subcontractors should carefully review the scope, pricing, and incorporated terms of their quotations before submitting them, recognizing that standard references such as the CISC Code may bring the CCA 1 and its dispute resolution provisions into play. Where a subcontractor objects to additional terms proposed by a contractor after the award, it should raise those concerns promptly, document them, and negotiate in good faith rather than simply refusing to proceed.
Contractors, for their part, should ensure that any terms they seek to add after the award are consistent with the subcontractor’s bid and the industry standard forms. They should document their efforts to resolve any disagreement, as Manorcore did by requesting further meetings with IBL.